Question: Exercise 1: Project Schedule Planning. Draw a network diagram, and answer the following questions. (Note: Network diagram can be drawn on a paper, scanned, and
Exercise 1:
Project Schedule Planning.
Draw a network diagram, and answer the following questions.
(Note: Network diagram can be drawn on a paper, scanned, and attached to your final assignment document.)
You are the project manager for a new project and have figured out the following dependencies:
- Activity 1 can start immediately and has an estimated duration of 2 weeks.
- Activity 2 can start after activity 1 is completed and has an estimated duration of 4weeks.
- Activity 3 can start after activity 2 is completed and has an estimated duration of 5 weeks.
- Activity 4 can start after activity 2 are completed and has an estimated duration of 2 weeks.
- Activity 5 can start after activity 3 and 4 are completed. This activity takes 4 weeks.
- What is the duration of the critical path?
- What is the critical path?
- What is the float of activity 3?
- What is the float activity of 4?
- The resource working on activity 4 is replaced with another resource who is less experienced. The activity will now take 4 weeks. How will this affect the project?