Question: Exercise 2 bf 2 Your Name: For the network below, calculate for each task, BCWP , BCWS , ACWP, CV , SV , CPI, SPI.

Exercise 2 bf 2
Your Name:
For the network below, calculate for each task, BCWP, BCWS, ACWP, CV, SV, CPI, SPI.
Calculate these numbers for the entire project as well.
For each of the seven tasks that make up the project above, assume the following:
Project is 16 days old--16 business days have transpired.
Fill out the table below:
Project is 16 days old--16 business days have transpired.
Calculate the following:
BAC=
EAC=
TAC=
?ETAC=
Comments on the status of your project:
Duration of the critical path is 30.
 Exercise 2 bf 2 Your Name: For the network below, calculate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!