Question: For the network below, calculate for each task, BCWP , BCWS , ACWP , CV , SV , CPI , SPI. Calculate these numbers for
For the network below, calculate for each task, BCWP
BCWS
ACWP CV
SV
CPI SPI. Calculate these numbers for the entire project as well. For each of the seven tasks that make up the project above, assume the following: Project is
days old
business days have transpired. For each task and for the entire project
bottom line
calculate BCWS
BCWP
CV
SV
CPI SPI. Project is
days old
business days have transpired. BAC
EAC
TAC
Comments on the status of your project:For the network below, calculate for each task, BCWP BCWS ACWP, CV SV CPI, SPI.
Calculate these numbers for the entire project as well.
B
E
A
C
G
F
D
For each of the seven tasks that make up the project above, assume the following:
Actual
Expenditures Duration
Percent
TASK
Complet
Expendit
uresDay
e
to Date
A
$
$
B
$
$
C
$
$
D
$
$
E
$
$
F
G
$
Project is days old business days have transpired.
$
SO
SO
TASK
TOTAL
BUDGET
ACWP
BCWS
BCWP
COMP
CV
SV
AC
PV
EV
A
$
$
B
$
C
$
D
$
E
$
F
SO
G
SO
Totals
$
For each task and for the entire project bottom line calculate BCWS BCWP CV SV CPI, SPI.
Project is days old business days have transpired.
BAC
EAC
TAC
ETAC
Comments on the status of your project:
CPI
SPI
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
