Question: For the network below, calculate for each task, BCWP , BCWS , ACWP , CV , SV , CPI , SPI. Calculate these numbers for

For the network below, calculate for each task, BCWP
,
BCWS
,
ACWP, CV
,
SV
,
CPI, SPI. Calculate these numbers for the entire project as well. For each of the seven tasks that make up the project above, assume the following: Project is
1
4
days old
-
-
1
4
business days have transpired. For each task and for the entire project
(
bottom line
)
calculate BCWS
,
BCWP
,
CV
,
SV
,
CPI, SPI. Project is
1
4
days old
-
-
1
4
business days have transpired. BAC
=
,
EAC
=
TAC
=
,
=
Comments on the status of your project:For the network below, calculate for each task, BCWP, BCWS, ACWP, CV, SV, CPI, SPI.
Calculate these numbers for the entire project as well.
B/9
E/5
A/11
C/7
G/4
F/9
D/6
For each of the seven tasks that make up the project above, assume the following:
Actual
Expenditures | Duration
Percent
TASK
Complet
Expendit
ures/Day
e
to Date
A
100% $2,000
$10,000
11
B
100% $1,200
$9,000
9
C
30% $1,000
$4,000
7
D
20%
$1,500
$5,000
6
E
40% $1,500
$3,000
5
F
G
0%
0% $1,200
Project is 14 days old--14 business days have transpired.
$1,000
SO
9
SO
4
TASK
TOTAL
BUDGET
ACWP
BCWS
BCWP
%COMP
CV
SV
15
(AC)
(PV)
(EV)
A
$22,000
100%
$10,000
B
100%
$9,000
C
30%
$4,000
D
20% $5,000
E
40%
$3,000
F
0%
SO
G
0%
SO
Totals
$31,000
For each task and for the entire project (bottom line) calculate BCWS, BCWP, CV, SV, CPI, SPI.
Project is 14 days old--14 business days have transpired.
BAC=
EAC =
TAC =
ETAC =
Comments on the status of your project:
CPI
SPI

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!