Question: Exercise 2 : Consider the table below. Use the PERT method to determine the total project time and the critical path: table [ [

Exercise 2:
Consider the table below. Use the PERT method to determine the total project time and the critical path:
\table[[Task,Preceding task,Time required],[A,NONE,14],[B,NONE,17],[C,A,12],[D,B,C,10],[E,C,D,5],[F,D,3],[G,E,F,11]]
 Exercise 2: Consider the table below. Use the PERT method to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer