Question: Exercise ( 2 ) : For the data given in the following table, it is required to: Draw the arrow network. Calculate ES , EF

Exercise (2):
For the data given in the following table, it is required to:
Draw the arrow network.
Calculate ES, EF, LS, and LF for each activity.
Calculate the total project duration.
Calculate total float and free float for each activity.
Indicate the critical path.
\table[[Activity,Events,\table[[Pessimistic],[Duration]],\table[[Most Likely],[Duration]],\table[[Optimistic],[Duration]]],[From,To,4,2],[A,1,2,9,6,3],[B,1,3,14,6,4],[C,2,4,16,7,4],[D,3,4,20,6,4],[E,3,5,19,5,3],[F,4,6,12,5,4],[G,5,7,10,4,4],[H,7,8,8,5,2],[I,6,8,19,4,1],[J,6,9,14,6,4],[K,9,10,19,6,5],[L,8,10,---------,,],[Dummy,4,5,----,--19,]]
Exercise (3):
Given the following network and PERT activity time estimates, determine the expected project completion time and variance, and the probability that the project will be completed in 28 days or less.
\table[[Activity,Time Estimates (weeks)],[\table[[Optimistic],[(a)]],\table[[Most likely],[(m)]],\table[[Pessimistic],[(b)]]],[(1-2),5,8,17],[(1-3),7,10,13],[(2-3),3,5,7],[(2-4),1,3,5],[(3-4),4,6,8],[(3-5),3,3,3],[(4-5),3,4,5]]
Exercise ( 2 ) : For the data given in the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!