Question: For the data given in the following table, it is required to: Draw the network. Calculate ES, EF, LS, and LF for each activity. Calculate
For the data given in the following table, it is required to:
- Draw the network.
- Calculate ES, EF, LS, and LF for each activity.
- Calculate the total project duration.
- Calculate total float and free float for each activity.
- Indicate the critical path.
| No. | Activity name | Duration (days) | Successor | Relationships (dependencies) | Lead/lag (days) |
| 1 | Make specification | 10 | 2 4 | Finish - to- start Finish - to- start | 0 0 |
| 2 | Make drawings | 50 | 3 5 6 | Start- to- start Finish - to- start Finish - to- start | +10 0 0 |
| 3 | Conclude steel purchase | 25 | 6 | Finish - to- start | 0 |
| 4 | Buy equipment | 20 | 7 | Finish - to- start | 0 |
| 5 | Obtain authorizations | 30 | 8 | Finish - to- start | 0 |
| 6 | Pre- producing sections | 25 | 9 | Finish- to- start | 0 |
| 7 | Run function tests | 10 | 9 | Finish - to- start | 0 |
| 8 | Make board folders | 20 | 10 | Finish - to- start | 0 |
| 9 | Carry out assembly | 70 | 10 | Finish - to- start | 0 |
| 10 | Inspection | 5 | None |
|
|