Question: Exercise 3 : Scheduling Project Instruction: Below is information about a Consumer Market Study Project. table [ [ Activity ID , Activity,Predecessor,Responsibility, table
Exercise : Scheduling Project
Instruction:
Below is information about a Consumer Market Study Project.
tableActivity IDActivity,Predecessor,Responsibility,tableEstimated DurationDayIdentify Target Customers,,Susan,Develop Draft Questionnaire,Susan,PilotTest Questionnaire,Susan,tableReview Comments and FinalizeQuestionnaireSusan,Prepare Mailing Labels,Steve,Print Questionnaire,Steve,Develop Data Analysis Software,Andy,Develop Software Test Data,Susan,tableMail Questionnaire and GetResponsesSteve,Test Software,Andy,Input Response Date,Jim,Analyze Results,Jim,Prepare Report,Jim,
Draw an activityonnode AON networkand copy into Word document or attach file. Please use the template. AON Template.xlsx
Identify the ES EF LS LF critical path, total float, and free float using the critical path algorithm. The SchedulingProjectExercise Excel file SchedulingProjectExercise.xls or found under Files contains the format for entering this information. Once you enter this information, cut and paste the Excel table on your word document.
Which of these tasks should the project manager track most closely?
What would happen if a new estimate for Activity "Prepare Mailing Labels," increases its expected duration from two days to ten days? Would the project take longer? Would anything else change? Explain your answer.
Draw a ESEF Gantt chart for the original project. You may use Excel to develop the chart. Do not forget to paste the Excelbased Gantt chart into your Word document.
Please put this in this format on excel. Activity on Node TemplateExercise : Scheduling Project
Instruction:
Below is information about a Consumer Market Study Project.
tableActivity IDActivity,Predecessor,Responsibility,tableEstimated DurationDayIdentify Target Customers,,Susan,Develop Draft Questionnaire,Susan,PilotTest Questionnaire,Susan,tableReview Comments and FinalizeQuestionnaireSusan,Prepare Mailing Labels,Steve,Print Questionnaire,Steve,Develop Data Analysis Software,Andy,Develop Software Test Data,Susan,tableMail Questionnaire and GetResponsesSteve,Test Software,Andy,Input Response Date,Jim,Analyze Results,Jim,Prepare Report,Jim,
Draw an activityonnode AON networkand copy into Word document or attach file. Please use the template. AON Template.xlsx
Identify the ES EF LS LF critical path, total float, and free float using the critical path algorithm. The SchedulingProjectExercise Excel file SchedulingProjectExercise.xls or found under Files contains the format for entering this information. Once you enter this information, cut and paste the Excel table on your word document.
Which of these tasks should the project manager track most closely?
What would happen if a new estimate for Activity "Prepare Mailing Labels," increases its expected duration from two days to ten days? Would the project take longer? Would anything else change? Explain your answer.
Draw a ESEF Gantt chart for the original project. You may use Excel to develop the chart. Do not forget to paste the Excelbased Gantt chart into your Word document.
Please put it in this format on excel, thank you!
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock