Question: Exercise 9.29 Suppose that we add some duration estimates to each of the activities from Exercise 9.28 0. A portion of the revised table is

Exercise 9.29 Suppose that we add some duration

Exercise 9.29 Suppose that we add some duration estimates to each of the activities from Exercise 9.28 0. A portion of the revised table is shown here. Recreate the network diagram for this project and note how MS Project uses nodes to identify activity durations, start and finish dates, and predecessors. What is the critical path for this network diagram? How do we know? Activity Duration Predecessors A-Survey site 5 days B - Install sewer and storm drainage 9 days A A C- Install gas and electric power lines 4 days A D- Excavate site for spec house 2 days B, C E-Pour foundation - 2 days D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!