Question: Suppose that we add some duration estimates to each of the activities from exercise 9.1. A portion of the revised table is shown here. Recreate
.png)
Activity A -Survey site B-Install sewer and storm drainage C-Install gas and electric power lines D Excavate site for spec house E- Pour foundation DurationPredecessors 5 days 9 days 4 days 2 days 2 days B, C
Step by Step Solution
3.40 Rating (159 Votes )
There are 3 Steps involved in it
Entering the above values and durations the network diagram would res... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
663-B-M-L-P-M (2123).docx