Suppose that we add some duration estimates to each of the activities from Exercise 9.28. A portion

Question:

Suppose that we add some duration estimates to each of the activities from Exercise 9.28. A portion of the revised table is shown here. Recreate the network diagram for this project and note how MS Project uses nodes to identify activity durations, start and finish dates, and predecessors. What is the critical path for this network diagram? How do we know?image text in transcribed

Exercise  9.28

Suppose we have a complete activity predecessor table (shown here) and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter the activities and their predecessors and create a complete activity network diagram for this project.image text in transcribedimage text in transcribed

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: