Question: EXERCISE A - - Develop the network diagram for the project below and show the ES , EF , LS , LF dates and indicate

EXERCISE A --
Develop the network diagram for the project below and show the ES,EF,LS,LF dates and indicate critical path. Complete the resource leveling BAR chart - to insure there are no more than 9 laborers per day.
\table[[Activity,Duration (Days),IPA,Laborers],[A,2,-,3],[B,4,A,2],[C,6,A,4],[D,9,A,3],[E,5,B,4],[F,7,B, C,2],[G,3,D, E, F,4]]