Question: Exercise: Production capacity 2. Total 1-shift production time available (excluding break time) is 7.5 hours. There are 2 shifts per day. Average downtime per day
Exercise: Production capacity 2. Total 1-shift production time available (excluding break time) is 7.5 hours. There are 2 shifts per day. Average downtime per day (not included change over time) is 40 minutes. Determine the available time for changeovers per day and the desirable number of changeovers per day Determine best batch sizes