Question: Exhibit 1 PROJECT DESCRIPTION AND TIME ESTIMATES ( WEEKS ) table [ [ Task , table [ [ Description ] , [ optimistic

Exhibit 1
PROJECT DESCRIPTION AND TIME ESTIMATES (WEEKS)
\table[[Task,\table[[Description],[optimistic]],\table[[Most],[likely]],\table[[Most],[pessimistic]],IP,],[A,Requirements,3,4,6,None],[B,Market assessment,4,7,10,A],[C,Design,5,6,9,A],[D,Development,6,7,16,C],[E,Testing,7,9,10,D],[F,Revising,4,5,6,B, E],[G,Documentation,3,6,10,D],[H,Quality assurance,3,5,7,C, E],[I,Pricing,2,2,2,B],[J,Production,3,4,14,F, G, H, I],[K,Distribution,2,3,4,J]]
Exhibit 2
PROJECT CRASH DATA
\table[[Task,Normal costs ($),Crash time (weeks),Crash costs ($)],[A,10,000,3,10,000],[B,20,000,6,25,000],[C,15,000,5,30,000],[D,45,000,6,65,000],[E,10,000,8,20,000],[F,15,000,4,18,000],[G,20,000,4,30,000],[H,10,000,3,15,000],[I,5,000,2,5,000],[J,40,000,5,50,000],[K,15,000,2,25,000]]1. Draw the project network diagram and calculate the following: ES, EF, LS, LF, total slack, free slack, and safety slack.
2. What is the estimated completion time for this project? What is the estimated project budget? What is the probability that the project can be completed in 35 weeks?
3. Assume that partial crashing is allowed. What is the minimum expected time in which the project can be completed? What is the probability of completing the project in this time?
4. What is the additional cost for reducing the project time to the required 35 weeks? Which specific tasks do you recommend crashing in order to achieve this milestone?
5. What is the impact on the crashing solution if the expected time for task B is increased from 7 weeks to 9 weeks? Explain with supporting evidence.
6. What is the impact on the crashing solution if the expected time for task H is decreased to 3 weeks? What if the expected time for task E is decreased to 8 weeks? Explain with supporting evidence.
 Exhibit 1 PROJECT DESCRIPTION AND TIME ESTIMATES (WEEKS) \table[[Task,\table[[Description],[optimistic]],\table[[Most],[likely]],\table[[Most],[pessimistic]],IP,],[A,Requirements,3,4,6,None],[B,Market assessment,4,7,10,A],[C,Design,5,6,9,A],[D,Development,6,7,16,C],[E,Testing,7,9,10,D],[F,Revising,4,5,6,B, E],[G,Documentation,3,6,10,D],[H,Quality

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!