Question: Exhibit 4 . 1 3 : Work Breakdown Structure and Activities for the Cell Phone Design Project MAJOR SUBPROJECTS / ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION

Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS)
Product Specifications (P)
Market research P14
Overall product specifications P2 P13
Hardware P3 P25
Software P4 P35
Supplier specifications (S)
Hardware S1 P45
Software S2 P46
Product design (D)
Battery D1 S11
Display D2 S12
Camera D3 S11
Outer cover D4 D1, D2, D34
Product integration (I)
Hardware I1 D43
User interface I2 D24
Software coding I3 I24
Prototype testing I4 I1, I34
Subcontracting (V)
Suppliers selection V1 S1,S210
Contract negotiation V2 I4, V13
a. Calculate the start and finish times for each activity. (Leave no cells blank - be certain to enter "0" wherever required.)
b. Determine the minimum number of weeks for completing the project.
c. Find the activities that are on the critical path for completing the project in the shortest time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!