Question: Exhibit 4 . 1 3 : Work Breakdown Structure and Activities for the Cell Phone Design Project MAJOR SUBPROJECTS / ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION

Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS)
Product Specifications (P)
Market research P12
Overall product specifications P2 P11
Hardware P3 P23
Software P4 P34
Supplier specifications (S)
Hardware S1 P44
Software S2 P46
Product design (D)
Battery D1 S11
Display D2 S12
Camera D3 S11
Outer cover D4 D1, D2, D33
Product integration (I)
Hardware I1 D45
User interface I2 D23
Software coding I3 I23
Prototype testing I4 I1, I33
Subcontracting (V)
Suppliers selection V1 S1,S29
Contract negotiation V2 I4, V11
Determine the minimum number of weeks for completing the project.
You have been asked to study the impact of making two changes to how the project is organized. The first change involves using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P (product specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships within a subprojectall tasks within a subproject would be worked on at the same time and each would take the same amount of time as originally specified. With this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V.
The second change your boss would like you to select the suppliers during subproject P and have them work directly with the dedicated teams. This would involve adding an additional activity to subproject P called supplier selection and contract negotiation (P5) with a duration of 10 weeks. This new activity would be done in parallel with P1, P2, P3, and P4. Subprojects S and V would be eliminated from the project.
What would be the expected impact on how long it would take to complete the project if these changes were made? Note: The original precedence relations from part a no longer apply here and now all subprojects are strictly sequential.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!