Question: Exhibit A: Work Breakdown Structure and Activities for the Cell Phone Design Project MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS) Product Specifications (P) Market research

Exhibit A: Work Breakdown Structure and Activities for the Cell Phone Design Project

MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS)
Product Specifications (P)
Market research P1 1
Overall product specifications P2 P1 3
Hardware P3 P2 4
Software P4 P3 4
Supplier specifications (S)
Hardware S1 P4 4
Software S2 P4 6
Product design (D)
Battery D1 S1 1
Display D2 S1 3
Camera D3 S1 1
Outer cover D4 D1, D2, D3 3
Product integration (I)
Hardware I1 D4 5
User interface I2 D2 3
Software coding I3 I2 3
Prototype testing I4 I1, I3 3
Subcontracting (V)
Suppliers selection V1 S1 ,S2 9
Contract negotiation V2 I4, V1 1

Find the activities that are on the critical path for completing the project in the shortest time.

options:

a) P1-P2-P3-P4-S1-D3-D4-I1-I4-V2
b) P1-P2-P3-P4-S2-V1-V2
c) P1-P2-P3-P4-S1-D1-D4-I1-I4-V2
d) P1-P2-P3-P4-S1-D2-D4-I1-I4-V2

Determine the minimum number of weeks for completing the project (i.e., critical path)?

options:

a) 32
b) 31
c) 27
d) 30

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!