Question: Expected activity completion time can be calculated (where a = optimistic completion time, b = pessimistic completion time, and m = most likely completion time)

Expected activity completion time can be calculated (where a = optimistic completion time, b = pessimistic completion time, and m = most likely completion time) as:

Group of answer choices

t = (2a + 2m + 2b)/6

t = (a + m + b)/3

t = (a + 4m + b)/6

t = (a + 5m + b)/6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock