Question: In the t = (a + 4m + b)/6 calculation for expected activity completion time, the a refers to? Group of answer choices Pessimistic completion
In the t = (a + 4m + b)/6 calculation for expected activity completion time, the a refers to?
Group of answer choices
Pessimistic completion time
Most likely completion time
Optimistic completion time
Activity completion time variance