Question: In the t = ( a + 4 m + b ) / 6 calculation for expected activity completion time, the a refers to ?
In the t a m b calculation for expected activity completion time, the a refers to
Group of answer choices
Activity completion time variance
Pessimistic completion time
Most likely completion time
Optimistic completion time