Question: Name: Exercise 1) Float Activity Duration (Days) Dependency Start A Start 1 -1 B Start C A D A E C. D F B B

Name: Exercise 1) Float Activity Duration (Days)
Name: Exercise 1) Float Activity Duration (Days) Dependency Start A Start 1 -1 B Start C A D A E C. D F B B H F, G E, H End I 1) Draw the network diagram 2) List the network paths 3) Perform a forward pass and a backward pass 4) Determine the critical path(s) 5) Determine the float for each activity and for each path