Question: Explain how did you find the answer. Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number

Explain how did you find the answer.

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activity

Immediate Predecessor(s)

Time (days)

A

4

B

5

C

1

D

B

10

E

A, D

3

F

C

5

G

E, F

8

This exercise contains only parts b, c, and d.

b) The critical activities for the leadership training program development project are ________

c) The project length for the leadership training program development project = ____days.

d) Slack time for each of the activities is:

Activity

Slack Time

A___

B

___

C

___

D

___

E

___

F

___

G

___

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!