Question: how do i find the slack? Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a umber of
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a umber of activities that must be completed before a training program of this nature coutd be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessnrisl Time ifauel ES EF LS LF SLACK (LF-EF) b) The critical activities for the leadership training program development project are s-D-E-6 c) The project length for the leadership training program development project = ? enter your response here days. 29 days. d) Slack time for each of the activities is