Question: Question 19 (2 points) v' Saved An agile development team has completed four iterations A, B, C, and D whose durations were 3 weeks,

Question 19 (2 points) v' Saved An agile development team has completed four iterations A, B, C, and D whose durations were 3 weeks, 2 weeks, 4 weeks, and 3 weeks respectively. The story points completed in each iteration were 19, 13, 29, and 23, respectively. Based solely on the team's velocity_(measured in week). roughly how many story points might they be expected to complete in the next 5-week long iteration? (VVhile teams usually plan iterations of equal duration, it is possible to sometimes have slightly unequal duration.) C) 18 @ 35 0 45 027