Question: Question 19 (2 points) Saved An agile development team has completed four iterations A, B, C, and D whose durations were 3 weeks, 2 weeks,

Question 19 (2 points) Saved An agile development team has completed four iterations A, B, C, and D whose durations were 3 weeks, 2 weeks, 4 weeks, and 3 weeks respectively. The story points completed in each iteration were 19, 13, 29, and 23, respectively. Based solely on the team's velocity (measured in story points per week) roughly how many story points might they be expected to complete in the next 5-week long iteration? (While teams usually plan iterations of equal duration, it is possible to sometimes have slightly unequal duration.) O 18 35 O 45 27