Question: f an activity whose normal duration is 1 5 days can be shortened to 1 0 days for an added cost of $ 2 ,

f an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, the crash cost per period is
Question 33 Select one:
A.
$20,000.
B.
$400.
C.
$30,000.
D.
$2,000.
E.
$10,000.