Question: f the earned value ( EV ) = 3 5 0 , actual cost ( AC ) = 4 0 0 , planned value (

f the earned value (EV)=350, actual cost (AC)=400, planned value (PV)=325, what is the CPI?
Question 9Select one:
a.
1.08
b.
0.93
c.
1.14
d.
0.88