Question: f. The lead time for each component (Buy it or make it) is the following: Component Lead Time * A 2 days The order to
| f. The lead time for each component (Buy it or make it) is the following: | |||||||||
| Component | Lead Time * | ||||||||
| A | 2 days | The order to Canadian Tire should be delivered on Nov/30/2006 at | |||||||
| B | 5 days | 5:00 PM | |||||||
| C | 5 days | Final assembly of Product A should start on __________ | |||||||
| D | 5 days | ||||||||
| E | 3 Days | Assembly B should start on _______ | |||||||
| F | 3 Days | ||||||||
| G | 3 Days | Sub-assembly E should start on _________ | |||||||
| H | 2 Days | ||||||||
| I | 2 Days | Component I should start on _________ | |||||||
| * Note: The lead times are in working days (Monday to Friday). | |||||||||
| S | S S | S S | S | S | S S | ||||
| 1 2 3 | 4 5 6 | 7 8 9 | 10 11 12 | 13 14 15 | 16 17 18 | 19 20 21 | 22 23 24 | 25 26 27 | 28 29 30 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock