Question: FedEX manager wants to control a packaging process. Last week, he randomly selects 4 packages and weighs. From the past data, he knows the process

FedEX manager wants to control a packaging process. Last week, he randomly selects 4 packages and weighs. From the past data, he knows the process standard deviation which is 2 ounces. The data from that activity appear below.

FedEX manager wants to control a packaging

Calculate upper and lower 3-sigma x-bar chart control limits that allow for natural variations. Based on the x-bar chart, is this process in control?

options:

Process is not in control

Process is in control

Weight Day Package 1 Package 2 Package 3 Package 4 Monday 23 22 23 24 Tuesday 23 21 19 21 Wednesday 20 19 20 21 Thursday 18 19 20 19 Friday 18 20 22 20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!