Question: Figure 1- Using the same figure as in #1, perform resource-limited scheduling. Assume that you have only three workers available at any given time. Use

Figure 1-

Figure 1- Using the same figure as in #1, perform

Using the same figure as in #1, perform resource-limited scheduling. Assume that you have only three workers available at any given time. Use slack to determine priority (. MUST SHOW ITERATIONS TO GET FULL CREDIT (Similar to Figures 6.10, 6.11, 6.12, 6.13)

Task 1 (2 workers) 1 1 1 Task 2 (1 worker) 1 Task 3 (3 workers) 1 Task 4 (2 workers) Task 5 (1 worker) 1 Task 6 (3 workers) Day 1 2 3 4 5 6 7 8 9 10 Workers 6 6 6 4 2 3 3 4 3 3 (Use the following blank table to assist in answering.)