Question: Figure to accompany Table 7.7 Od E 4 Table 7.7 AVAILABLE WEEKS OF CRASHING NORMAL COST ($000s) 8 CRASHING COST / WEEK ACTIVITY A NORMAL
Figure to accompany Table 7.7 Od E 4 Table 7.7 AVAILABLE WEEKS OF CRASHING NORMAL COST ($000s) 8 CRASHING COST / WEEK ACTIVITY A NORMAL TIME 4 3 4 5 CRASH TIME 2 2 4 B 9 CRASH COST ($000s) 14 11 10 15 14 6 C D E 10 10 11 6 3 1 1 4 F 1 Indirect project cost = $2000 per week Penalty cost = $5000 per week past week 12 What is the total project cost before crashing? O $54,000 $92,000 $72,000 O $28,000