Question: Figure to accompany Table 7.7 Table 7.7 ACTIVITY NORMAL TIME CRASH TIME NORMAL COST ($000s) CRASH COST ($000s) AVAILABLE WEEKS OF CRASHING CRASHING COST /

Figure to accompany Table 7.7 Table 7.7

ACTIVITY NORMAL TIME CRASH TIME NORMAL COST ($000s) CRASH COST ($000s) AVAILABLE WEEKS OF CRASHING CRASHING COST / WEEK
A 4 2 8 14
B 3 2 9 11
C 4 4 10 10
D 5 3 10 15
E 4 1 11 14
F 1 1 6 6

What is the critical path for the project shown in the above network and Table 7.7, using the normal times?

Group of answer choices

A-B-C-D-E-F

A-C-E-F

A-B-D-F

A-C-D-F