Question: Figure to accompany Table 7.7 Table 7.7 ACTIVITY NORMAL TIME CRASH TIME NORMAL COST ($000s) CRASH COST ($000s) AVAILABLE WEEKS OF CRASHING CRASHING COST /
Figure to accompany Table 7.7 Table 7.7
| ACTIVITY | NORMAL TIME | CRASH TIME | NORMAL COST ($000s) | CRASH COST ($000s) | AVAILABLE WEEKS OF CRASHING | CRASHING COST / WEEK |
| A | 4 | 2 | 8 | 14 | ||
| B | 3 | 2 | 9 | 11 | ||
| C | 4 | 4 | 10 | 10 | ||
| D | 5 | 3 | 10 | 15 | ||
| E | 4 | 1 | 11 | 14 | ||
| F | 1 | 1 | 6 | 6 |
Determine the information missing from Table 7.7; then answer the following questions. How many week(s) of crashing are available for activity D in Table 2.9?
Group of answer choices
1
2
0
6