Question: Fill in the table below with the activity times after crashing to show the resulting schedule. ( Enter your responses as whole numbers. ) Activity
Fill in the table below with the activity times after crashing to show the resulting schedule. Enter your responses as whole numbers.
Activity
Time according to schedule weeks
Activity
Time according to schedule weeks
A
enter your response here
F
enter your response here
B
enter your response here
G
enter your response here
C
enter your response here
H
enter your response here
D
enter your response here
I
enter your response here
E
enter your response here
Part
The cost of shortening of project is $
enter your response here. Enter your response as a whole number.