Question: Final Exam W 2 4 Saved Help Save & From the following information, develop an AON project network. Complete the forward and backward pass, compute

Final Exam W24
Saved
Help
Save &
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
\table[[ID,Description,Predecessor,Time],[A,Survey site,None,6],[B,Excavate site,A,5],[C,Install power lines,B,4],[D,Install drainage,B,1],[E,Pour foundation,C, D,3]]
01:28:17
\table[[The project will take,days.],[The critical path is,],[The late start on Activity C is,days.],[The slack on Activity C is,days.],[The slack on Activity D is,days.],[The early start on Activity E is,days.]]
Mc
Prev
43 of 53
Next
51F
Cloudy
Search
 Final Exam W24 Saved Help Save & From the following information,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!