Question: Final Exam W 2 4 Saved Help Save & From the following information, develop an AON project network. Complete the forward and backward pass, compute
Final Exam W
Saved
Help
Save &
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
tableIDDescription,Predecessor,TimeASurvey site,None,BExcavate site,ACInstall power lines,BDInstall drainage,BEPour foundation,C D
::
tableThe project will take,days.The critical path isThe late start on Activity isdays.The slack on Activity isdays.The slack on Activity isdays.The early start on Activity isdays.