Question: Find out the project duration, four times (EST, EFT, LST, and LFT), critical activities and the slack (total float) for each activity. Activity Requirement Duration
Find out the project duration, four times (EST, EFT, LST, and LFT), critical activities and the slack (total float) for each activity.
| Activity | Requirement | Duration |
| A | - | 7 |
| B | - | 4 |
| C | A | 5 |
| D | A, B | 6 |
| E | A, B | 8 |
| F | C | 9 |
| G | D, F | 3 |
| H | E, G | 4 |