Table below presents the activities of a project.
|
|
|
|
| Needed Resources (man) | |
| Number | Activity | Duration (day) | Pre-Requisite | Man/day | Cumulative |
| | A | 4 | - | 1 | 4 |
| | B | 5 | A | 1 | 5 |
| | C | 6 | A | 1 | 6 |
| | D | 6 | C | 1 | 6 |
| | E | 16 | A | 1 | 16 |
| | F | 4 | E | 1 | 4 |
| | G | 10 | E | 1 | 10 |
| | H | 4 | F, B, D | 1 | 4 |
- Draw the critical path method (AON) and find out the project duration, four times (EST, EFT, LST, and LFT), critical activities and the slack (total float) for each activity. (1)
- Draw Gantt chart based on the earliest times. (1)
- Draw the Daily Resources Diagram before smoothing (leveling of resources) and after smoothing (leveling of resources). (1)
- Draw S curve before and after leveling. (1)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock