Question: Find the slack for activity C AO 7 7 2 9 C7 19 12 14 26 F 26 32 6 26 32 Start Finish BO

 Find the slack for activity C AO 7 7 2 9

Find the slack for activity C AO 7 7 2 9 C7 19 12 14 26 F 26 32 6 26 32 Start Finish BO 9 9 09 D 9 17 8 9 17 E 17 26 9 17 26 G 26 31 5 27 32 Select one: a. 2 weeks b. 14 weeks c. 12 weeks d. 7 weeks