Question: Finding Different Paths and Critical Path : A - B - D - F = 3 + 3 + 3 + A - C -

Finding Different Paths and Critical Path :
A-B-D-F =3+3+3+
A-C-E-F =3+4+4+_=12(i.e. Duration for Activity F is 1(1*1))
Therefore
x =1
Paths:
A-B-D-F =3+3+3+1=10
A-C-E-F =3+4+4+1=12(Critical Path)
Explanation:
Based on the given Network paths and Critical Path . The path which is having Maximum Duration is Critical Path.