Question: Find:Job sequence, average flow time, average da job Processing time( days) Due Date( days) a 10 10 b 5 15 c 7 17 d 8

  1. Find:Job sequence, average flow time, average da
job Processing time( days) Due Date( days)
a 10 10
b 5 15
c 7 17
d 8 20
e 6 22
f 9 21
j 4 15

  1. There are seven jobs that must be processed in two operations: A and B. All seven jobs must go through A and B in that sequence - A first, and the B. a)Find the job sequence by Johnson's rule b) What is the total completion time for all seven jobs
job

Process A

(hours)

Process B

(hours)

a 9 6
b 8 5
c 7 7
d 6 3
e 1 2
f 2 6
j 4 7