FIRST, COPY THE PROJECT SHOW BELOW ON YOUR SCRATCH PAD. SECOND, DO A FORWARD AND BACKWARD PASS TO COMPUTE THE EARLY START, EARLY FINISH, LATE FINISH, LATE START, AND SLACK FOR ALL ACTIVITIES. KEEP YOUR SOLUTION NEAR YOU. THIRD, YOU WILL ANSWER THREE (3) QUESTIONS BASED ON THIS PROJECT. THOSE QUESTIONS WILL POP-UP RANDOMLY. T (3) H (2) R (4) Z (3) W(61 K (5) Given the network shown above, what is the slack time for activity H? 2 0 3 O 5