Question: FIRST, COPY THE PROJECT SHOW BELOW ON YOUR SCRATCH PAD. SECOND, DO A FORWARD AND BACKWARD PASS TO COMPUTE THE EARLY START, EARLY FINISH, LATE

FIRST, COPY THE PROJECT SHOW BELOW ON YOUR SCRATCH PAD. SECOND, DO A FORWARD AND BACKWARD PASS TO COMPUTE THE EARLY START, EARLY FINISH, LATE FINISH, LATE START, AND SLACK FOR ALL ACTIVIT KEEP YOUR SOLUTION NEAR YOU. THIRD, YOU WILL ANSWER THREE (3) QUESTIONS BASED ON THIS PROJECT THOSE QUESTIONS WILL POP-UP RANDOMLY. T(B) H (2) R (4) Z (3) W(6) K (5) Given the network shown above, what is the latest start time for activity H? 010 O 13 015 12