Question: Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is

Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.

Job

Processing Time (days)

Due Date (days)

A

2

9

B

6

16

C

4

17

D

8

15

E

9

19

Using the earliest due date (EDD) rule, the average lateness for the five jobs is: