Question: Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is

Five jobs are ready for processing at time zero

Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date (days) A 9 18 B 4 14 5 10 D 6 19 E 3 13 Using the earliest due date (EDD) rule, the average flow time for the five jobs is O a. more than 8 but less than or equal to 10 days. b. more than 14 but less than or equal to 16 days. c. more than 10 but less than or equal to 12 days. O d. more than 12 but less than or equal to 14 days