Question: Five jobs are waiting for processing through two work centres. Their processing time (in minutes) at each work centre is contained in the table below.
Five jobs are waiting for processing through two work centres. Their processing time (in minutes) at each work centre is contained in the table below. Each job requires work centre Sigma before work centre Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs?
| Job | Sigma | Delta |
| R | 40 | 10 |
| S | 25 | 30 |
| T | 50 | 20 |
| U | 35 | 35 |
| V | 55 | 15 |
| RSTUV | |
| SVTRU | |
| SUTVR | |
| VRUST | |
| SUVTR |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
