Question: Five jobs are waiting for processing through two work centres. Their processing time (in minutes) at each work centre is contained in the table below.

Five jobs are waiting for processing through two work centres. Their processing time (in minutes) at each work centre is contained in the table below. Each job requires work centre Alpha before work centre Beta. What is the minimum time for completion of all jobs?

Job
Work Centre Alpha
Work centre Beta
ER
20
10
BS
25
35
DT
50
20
AU
15
35
CV
55
75

200

195

165

185

175

Step by Step Solution