Question: Five jobs are waiting for processing through two work centres. Their processing time (in minutes) at each work centre is contained in the table below.
Five jobs are waiting for processing through two work centres. Their processing time (in minutes) at each work centre is contained in the table below. Each job requires work centre Alpha before work centre Beta. What is the minimum time for completion of all jobs?
Job | Work Centre Alpha | Work centre Beta |
ER | 20 | 10 |
BS | 25 | 35 |
DT | 50 | 20 |
AU | 15 | 35 |
CV | 55 | 75 |
| 200 | ||
| 195 | ||
| 165 | ||
| 185 | ||
| 175 |