Question: Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the earliest due date priority rule, in which
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the earliest due date priority rule, in which order should the jobs be processed?
Using the critical ratio priority rule, in which order should the jobs be processed? All dates are specified as days from today.
| Job | Processing Time (days) | Job due date (days) |
| A | 4 | 7 |
| B | 2 | 4 |
| C | 8 | 11 |
| D | 3 | 5 |
| E | 5 | 8 |