Question: Five jobs are waiting to be processed. Their processing times and due dates are given below. a. Show the order of each job using each
Five jobs are waiting to be processed. Their processing times and due dates are given below.
a. Show the order of each job using each of the four priority rules, showing total processing time, total flow time, and total job lateness for each.
| Job | Processing Time (days) | Job due date (days) |
| A | 4 | 7 |
| B | 7 | 4 |
| C | 8 | 11 |
| D | 3 | 5 |
| E | 5 | 8 |