Question: Fo For the project tasks and precedence tasks below: A) List all of the pathways from the start to the finish of the project B)
Fo
For the project tasks and precedence tasks below:
A) List all of the pathways from the start to the finish of the project
B) List the duration of each of the pathways
C) Which pathway is the critical path (and why is it the critical path)?
D) How long is the project expected to take to complete?
| Activity | Immediate Predecessor | Task Times | Slack times |
| A | - | 4 |
|
| B | - | 5 |
|
| C | A | 2 |
|
| D | B | 7 |
|
| E | D | 4 |
|
| F | E | 2 |
|
| G | C | 4 |
|
| H | D, G | 7 |
|
| I | D | 9 |
|
| J | F, H | 7 |
|
| K | I | 4 |
|