Question: Following table shows the tasks carried down during a project. Create a Custom Field that calculates the Remaining Duration of the tasks. Note that Tasks

Following table shows the tasks carried down during a project. Create a Custom Field that calculates the Remaining Duration of the tasks. Note that Tasks A and C have started a day late.

Task name Duration Complete %

A 3 days 47%

B 3 days 21%

C 4 days 17%

D 2 days 73%

Step by Step Solution