Question: Following table shows the tasks carried down during a project. Create a Custom Field that calculates the Remaining Duration of the tasks. Note that Tasks
Following table shows the tasks carried down during a project. Create a Custom Field that calculates the Remaining Duration of the tasks. Note that Tasks A and C have started a day late.
Task name Duration Complete %
A 3 days 47%
B 3 days 21%
C 4 days 17%
D 2 days 73%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
